Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : PATNA-MUZZAFFARPUR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
671.30671.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1830.13001830.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20130/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
144.130

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.87Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks