Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46.

Reported Date : 26-DEC-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2022

Cost Overrun (%)-   10.46

Time Overrun (Months)-    125

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
12501380.731380.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1345.589.0701354.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20135/20245/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
96.64Completed

Monthly Status

Background Information

Out of total length of 148.300 Km, 142.870 Km has been completed. Balance work in 5.43 Km at three locations in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone