Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SRINAGAR TO BANIHAL.

Reported Date : 26-DEC-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    102

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1100.701100.7

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2924.0211.8250.482986.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20140/012/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Completed

Monthly Status

Background Information

Out of 65.41kms only 57.44 KM length has been completed and PCOD has been issued for the same. The rest have been assigned to a new contractor as balance work. The operation and maintenance activities are performed on the completed stretch in the month of December.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone