Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANING OF BRAHAMPORE-FARAKA.

Reported Date : 07-MAR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    127

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
998.790998.79

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2170.28002170.28

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20130/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
43.990

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.99Completed

Monthly Status

Background Information

Present Physical progress is 99.99%. Four laning work in total project length of 100.6 km has been completed except some finishing & minor works.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone