Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9.

Reported Date : 25-APR-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2022

Cost Overrun (%)-   21.92

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1266.601544.18

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1446.45001446.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20160/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The Completion Certificate for the project issued on 17.09.2019, Hence project has been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone