Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : REHABILITATION AND UPGRADATION OF NH-42 FROM KM 4-350 TO KM 75-600.

Reported Date : 02-DEC-24

MOU Status :

Monthly Report : 11 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
309.010309.01

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00274.36274.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20158/20175/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone