Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANING OF BAHARAGORA - SINGHARA.

Reported Date : 06-JAN-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    16

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1282.9401282.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
676.1129.350705.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20200/08/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.69Completed