Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : CONSTRUCTION OF ISLAMPUR BY PASS.

Reported Date : 05-DEC-22

Monthly Report : 11 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
361.15416363.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
276.7100276.71

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/02/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks