Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   20.26

Time Overrun (Months)-    106

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1655.011990.381990.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1795.916.812.31815.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20161/20206/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
267.816.89

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.8Ongoing

Monthly Status

Background Information

179.66 km is completed out of total length of 187.24 km. Physical progress achieved is 97.80%. Financial progress achieved is 99.32% Likely Completion date is 30.06.2025 Physical progress achieved so far is 97.8% .Out of 187.24 kms only 179.353 kms work has been completed. PCOD3 for a Km of 170.98 was issued on 24.03.2023. Likely Completion date is 31.12.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition6/20234/2025PendingImmediate1.04 Km length affected due to LA issues in Kumta & Ankola Taluk.
Others6/20234/2025PendingImmediate0.52 Km affected due to Public Demand for additional structures at Mudbhatkal, Kaikini & Vitthal ghat.
Utility shiftng6/20234/2025PendingImmediate1.14 Km is affected due to local issue such as sewer line repair / shifting.

Ongoing Milestone

Completed Milestone