Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 20.26
|
Time Overrun (Months)-
106
|
Total/Pending/Completed Milestone -
4
/
0
/
4
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
179.66 km is completed out of total length of 187.24 km.
Physical progress achieved is 97.80%.
Financial progress achieved is 99.32%
Likely Completion date is 30.06.2025
| Physical progress achieved so far is 97.8% .Out of 187.24 kms only 179.353 kms work has been completed. PCOD3 for a Km of 170.98 was issued on 24.03.2023. Likely Completion date is 31.12.2024. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Land Acquisition | 6/2023 | 4/2025 | Pending | Immediate | 1.04 Km length affected due to LA issues in Kumta & Ankola Taluk. |
Others | 6/2023 | 4/2025 | Pending | Immediate | 0.52 Km affected due to Public Demand for additional structures at Mudbhatkal, Kaikini & Vitthal ghat. |
Utility shiftng | 6/2023 | 4/2025 | Pending | Immediate | 1.14 Km is affected due to local issue such as sewer line repair / shifting. |
| Ongoing Milestone | | Completed Milestone | | |