Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -II.

Reported Date : 22-JUN-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
795.760686.13

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
669.9400669.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/05/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Final payment has been made

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks