Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    75

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1041.1567639.58

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
535.0318.70553.73

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20193/20257/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
89.240

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.57Ongoing

Monthly Status

Background Information

Physical progress achieved 97.57%. & Financial progress achieved is 96.81% sofar Out of 60.23 km only 58.61km work has been completed &PCC issued on 30.03.2023.Now Anticipated date of completion is 31.07.2025. """"""""""""""""""""""""""""""""""Physical progress achieved 95.57%. & Financial progress achieved is 94.36% sofar Out of 60.23 km only 58.61km work has been completed &PCC issued on 30.03.2023.Now Anticipated date of completion is 31.12.2024. """""""""""""""""""""""""""""""

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone