Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
75
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Physical progress achieved 97.57%. & Financial progress achieved is 96.81% sofar
Out of 60.23 km only 58.61km work has been
completed &PCC issued on 30.03.2023.Now Anticipated date of completion
is 31.07.2025. """"""""""""""""""""""""""""""" | """Physical progress achieved 95.57%. & Financial progress achieved is 94.36% sofar
Out of 60.23 km only 58.61km work has been
completed &PCC issued on 30.03.2023.Now Anticipated date of completion
is 31.12.2024. """"""""""""""""""""""""""""""" |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |