Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANNING OF LUDHIYANA- TALWANDI SECTION.

Reported Date : 08-DEC-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 11 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    24279

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
479479479

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
456.800456.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/03/20233/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1.661.66

Ministry Review Date

LatestLastPhysical Progress (%)Status
93.2Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone