Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   23.73

Time Overrun (Months)-    76

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2136.9726442644

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2362.9923.13.112386.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20184/20254/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
133.930

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.5Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone