Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF JABALPUR - LAKHNADON.

Reported Date : 22-JUN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    24248

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
928.830928.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
867.8300867.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/08/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

This Project was approved on March 2015 with Capital Investment of Rs. 928.83 Crores. Provisional COD has been issued on 12.02.2020. Present Physical progress is 100%.Completion certificate has been issued on 14.08.2020, and final payment has been made.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone