Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF SULTANPUR TO VARANASI (PKG-I).

Reported Date : 08-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   155.79

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1027.532950.042628.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2596.0352.9302648.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20187/20233/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
43.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.27Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone