Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 148.00 208.300 KM [PACKAGE-IV].

Reported Date : 07-JAN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2024

Cost Overrun (%)-   120.47

Time Overrun (Months)-    68

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1587.493473.593500

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2969.21386.923.523379.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/201912/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
129.930

Ministry Review Date

LatestLastPhysical Progress (%)Status
24-OCT-2196.47Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone