Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLY.

Reported Date : 25-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    75

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
701.4591.86701.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
381.830542.16923.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/201912/20236/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
239.310

Ministry Review Date

LatestLastPhysical Progress (%)Status
88Completed

Monthly Status

Background Information

Physical progress was achieved by EPC Contractor is 73.95% .Out of 45.14 kms only 35.616 kms work has been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone