Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING EXISTING KM 263.00 TO 328.00] ADDAHOLE TO BANTAWAL.

Reported Date : 09-JUN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2022

Cost Overrun (%)-   63.08

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
87001418.78

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
283.3800283.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project is foreclosed and split into 2 packages: 1)Four-Laning of the Bangalore-Mangalore section of NH-48 (New NH-75) from Design Chainage 270+270 (Periya Shanthi) to Design Chainage 318+755 (Bantwal) Including Six Lane Flyover at Kalladka Town from Design Chainage 311+040 to Design Chainage 314+080 on Engineering, Procurement and Construction (EPC) Basis in the State of Karnataka- 45 Kms. 2. Consultancy services for 4 L of Addahole (Near Gundya) to Bantwal Cross Section (Pkg-01) from Design Km. 255.703 to Design Km. 270.270 of NH-75 (Old NH-48)(Forest stretch )- 14.5 kms. Separate ID is created for the projects.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone