Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4 LANING FROM PHAGWARA TO RUPNAGAR.

Reported Date : 17-NOV-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 11 / 2022

Cost Overrun (%)-   94.94

Time Overrun (Months)-    24257

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1169.6102280

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1330.39001330.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/05/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone