Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING OF CHIKHLI TO TARSOD (FROM KM 360-422.700).

Reported Date : 30-DEC-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1071.6101048.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1227.6440.3611.271279.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/202112/202112/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
142.21251.09

Ministry Review Date

LatestLastPhysical Progress (%)Status
20-MAR-2298.5Completed

Monthly Status

Background Information

The four laning work is in progress and the concessionaire has achieved 98.50% of physical progress till November-2022. PCOD has been Issued to concessionaire. Project is at completion stage.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone