Reported Date :
01-MAY-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
32
|
Total/Pending/Completed Milestone -
4
/
1
/
3
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
The four laning work is progress and the concessionaire has achieved 84.76% of physical progress till March 2024.
The PCC has been issued to concessionaire w.e.f 12.03.2024.
Cumulative Expenditure in Previous Financial Year-765.95Cr
Cumulative Expenditure in Current Financial Year-96.28 Cr
Cumulative Expenditure Till now (March-2024) - 862.23 Cr
| The four laning work is progress and the concessionaire has achieved 84.45% of physical progress till February-2024. Provisional Completion Certificate/PCOD has been issued w.e.f. 12.03.2024. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |