Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING OF TARSOD-FAGNE(FROM KM 422.700-510.00).

Reported Date : 01-MAY-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1064.8801021

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
862.23096.28958.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/202112/20233/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
189.12226.58

Ministry Review Date

LatestLastPhysical Progress (%)Status
20-MAR-2284.76Completed

Monthly Status

Background Information

The four laning work is progress and the concessionaire has achieved 84.76% of physical progress till March 2024. The PCC has been issued to concessionaire w.e.f 12.03.2024. Cumulative Expenditure in Previous Financial Year-765.95Cr Cumulative Expenditure in Current Financial Year-96.28 Cr Cumulative Expenditure Till now (March-2024) - 862.23 Cr The four laning work is progress and the concessionaire has achieved 84.45% of physical progress till February-2024. Provisional Completion Certificate/PCOD has been issued w.e.f. 12.03.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone