Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SIX LANNING FROM KM. 401.200 TO 494.410 OF NH-8 ON HYBRID ANNUITY MODE UNDER NHDP-V(PKG VI)REG..

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   22.11

Time Overrun (Months)-    54

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1251.111527.751527.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
664.9219.210684.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20206/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
122.53300

Ministry Review Date

LatestLastPhysical Progress (%)Status
83.84Ongoing

Monthly Status

Background Information

Physical Progress of Project is 83.76% and Financial Progress of Project is 83.53% and length completed as per DBM is 87.67KM and BC is 86.06Km till 29.02.2023

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone