Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANNING OF TULJAPUR-AUSA SECTION.

Reported Date : 28-NOV-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 11 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    25

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
904.160904.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
000904.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20203/20223/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.51Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone