Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING OF BODHRE-DHULE SECTION(KM 390.000 TO 452.800).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
744.6401007

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
467.6500467.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20207/202212/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
169.33252.46

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.69Ongoing

Monthly Status

Background Information

The work of 4-laning is in progress. The physical progress is 97.69% and financial progress is 97.69%.The work of 4-laning is in progress. The physical progress is 68.23% and financial progress is 68.23%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks