Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANNING OF PORBANDAR DWARKA SECTION IN THE STATE OF GUJARAT.

Reported Date : 21-NOV-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 11 / 2022

Cost Overrun (%)-   1.78

Time Overrun (Months)-    16

Total/Pending/Completed Milestone - 3 / 0 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1958.882047.391993.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1116.85001116.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20200/010/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
01182.95

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

project complete since 13 October 2021.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone