Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SIX LANNING OF AUNTA-SIMARIA(GANGA BRIDGE WITH APPROACH ROADS) SECTION OF NH-31.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
950.6411611168.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1126.1730.1201156.29

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/202210/20248/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
137.650

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.56Ongoing

Monthly Status

Background Information

Physical Progress :- 99.56% Financial Progress :- 99.56% PCOD issued on 15.05.2025 Completed Length :-8.150 Km Physical Progress :- 76.88% Financial Progress :- 76.88% Length Completed till date is 4.90 km out of 8.15 Km

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks