Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SIX LANNING OF AUNTA-SIMARIA(GANGA BRIDGE WITH APPROACH ROADS) SECTION OF NH-31.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   22.9

Time Overrun (Months)-    39

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
950.6411611168.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
892.58176.756.891126.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/202210/20245/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
137.650

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

Physical Progress :- 97% Financial Progress :- 97% Length Completed till date is 7.00km out of 8.15 Km Physical Progress :- 76.88% Financial Progress :- 76.88% Length Completed till date is 4.90 km out of 8.15 Km

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone