Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : REHABILITATION AND UPGRADATION OF TWO LANING OF MAHESHKHUNT - SAHARSA - PURNEA SECTION PKG - I.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   26.72

Time Overrun (Months)-    44

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
573.7644.5726.99

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
443.5533.4415.34492.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202112/20248/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
202.310

Ministry Review Date

LatestLastPhysical Progress (%)Status
81.22Ongoing

Monthly Status

Background Information

Physical Progress :-81.83% Financial Progress :-76.39% Out of 90.00 kms only 76.600kms work has been completed"""""""""""""""Physical Progress :-73.55% Financial Progress :-68.82% Out of 90.00 kms only 76.200kms work has been completed"""""""""""""""

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone