Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : NAGAUR-BIKANER OF NH-11 (2L+PS) UNDER PPP..

Reported Date : 07-SEP-20

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 7 / 2020

Cost Overrun (%)-   26.62

Time Overrun (Months)-    78

Total/Pending/Completed Milestone - 4 / 3 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
378.070478.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
188.6500188.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20140/07/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone