Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : KHAMGAON TO SHEGAON.

Reported Date : 14-SEP-23

Monthly Report : 9 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
203.210203.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
163.8100163.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20190/09/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks