Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : MAJALGAON TO KAIJ.

Reported Date : 06-SEP-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 8 / 2021

Cost Overrun (%)-   0

Time Overrun (Months)-    25

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
413.990413.99

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
200.199.620299.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20190/08/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Physical progress for the month of July is 97.88%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone