Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : SALAIKHURD TO TIRORA.

Reported Date : 25-OCT-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 4 / 2 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
415.250415.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
274.0200274.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20190/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Physical progress for the month of March is 97.99%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks