Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : BAMNI TO NAVAEGAON.

Reported Date : 24-FEB-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 4 / 3 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
241.690241.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
16012.010172.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20200/01/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone