Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : FARDAPUR TO JALGAON.

Reported Date : 25-OCT-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 4 / 2 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
456.450456.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
427.4300427.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20190/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Physical progress for the month of March is 89.88%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks