Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : ISMAILABAD-NARNAUL PKG-8.

Reported Date : 01-NOV-22

Monthly Report : 10 / 2022

  

   

Total/Pending/Completed Milestone - 4 / 4 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1033.191044.321044.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
759.05152.530911.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/03/20223/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
158.69158.69

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks