Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs).
Project Name : NAGAUR-BIKANER SECTION FROM KM 177.00 TO KM 267.325 ON NH-89.

Reported Date : 14-JUL-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
370.360370.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
90.45181.360271.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20220/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone