Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4-LANING OF DEWAS-UJJAIN OF SECTION NH-148 NG FROM KM 0+000 TO KM 41.42 IN MP ON HAM MODE.

Reported Date : 03-OCT-23

Monthly Report : 9 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7161093.48716

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
289.96326.274.86621.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/202111/20237/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
45.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks