Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF ADDAHOLE TO BANTWAL CROSS SECTION INCLUDING FLYOVER AT KALLADKA TOWN.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1100.881687.311687.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1097.7751.277.221156.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/202111/202511/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
514.920

Ministry Review Date

LatestLastPhysical Progress (%)Status
80.3Ongoing

Monthly Status

Background Information

Physical progress achieved so far is 80.30%. Out of 48.485 Km only 48.12Km is completed. The anticipated date of completion is 30/11/2025Physical progress achieved so far is 56.5%. Out of 48.485 Km only 26.32 Km is completed. The anticipated date of completion is November 2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks