Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF ADDAHOLE TO BANTWAL CROSS SECTION.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   79.93

Time Overrun (Months)-    42

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
317.9572.01572.01

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
303.7456.621.87362.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20214/20254/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
44.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
97.42Ongoing

Monthly Status

Background Information

Out of 15.13 Km only 14.7 Km is completed. The Physical Progress achieved is 97.42%. The anticipated date of completion is 30.04.2025Out of 15.13 Km only 12.66 Km is completed. The Physical Progress achieved is 85.5%. The anticipated date of completion is 31.05.2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone