Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF SANGLI - SOLAPUR (PKG III) [WATAMBARE-MANGALWEDHA] FROM KM 276.0 - KM 321.60.

Reported Date : 16-MAR-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    26

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
9570957

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
781.487.95552.481341.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20200/02/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone