Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : FOUR LANING OF SANGLI - SOLAPUR (PKG I) [SANGLI - BORGAON KM 182.556 - KM 224.00].

Reported Date : 06-MAR-23

Monthly Report : 2 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1102.41040.261102.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
04.03550.84554.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20236/20223/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
74.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
96.52Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks