Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L OF INDAPUR TO TONDLE (PKG-III) FROM KM.84.550 TO KM. 131.00 OF NH-965G (SAINT TUKARAM MARG).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
667.66666.21666.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
598.6511.980610.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20231/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
166.48166.48

Ministry Review Date

LatestLastPhysical Progress (%)Status
3Ongoing

Monthly Status

Background Information

"Physical Progress=95% Financial Progress=91%""Physical Progress=79% Financial Progress=67%"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks