Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : CONSTRUCTION OF FOUR LANE RINGROAD BYPASS SRINAGAR CITY.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2919.9602919.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2281.4736.3517.172334.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/202410/202510/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
222.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

The current physical progress is 70%The Physical Progress till current month is: 42.80%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks