Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 26.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1542.0201542.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
661.7260.8431.94954.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20240/011/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
567.730

Ministry Review Date

LatestLastPhysical Progress (%)Status
67.85Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone