Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 27.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1185.6901185.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
948.2331.93.25980.41

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20248/20258/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
237.290

Ministry Review Date

LatestLastPhysical Progress (%)Status
93.52Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks