Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 29.

Reported Date : 05-OCT-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1523.7701523.77

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
805.12157.94.08963.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20230/010/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
186.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project Completed on 16/05/2023 COD is under process with Competent Authority

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks