Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 31.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1604.0601604.06

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1235.256.154.121245.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20240/08/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
53.330

Ministry Review Date

LatestLastPhysical Progress (%)Status
95.73Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks