Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 6L OF KAGAL-SATARA SECTION FROM KM 592.240 TO KM 658.000 OF NH-48 (PKG-I).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 4 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1025.201025.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
428.4924.93.94457.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20250/01/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
871.830

Ministry Review Date

LatestLastPhysical Progress (%)Status
44.61Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks