Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L MEDINIPUR TO BALLUPUR FROM KM. 458.65 TO KM. 487.65 OF NH-07(PKG-2).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1092.91092.91092.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
460.623.30463.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20256/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1036.941036.94

Ministry Review Date

LatestLastPhysical Progress (%)Status
81.2Ongoing

Monthly Status

Background Information

The project will serve as a section of Poanta Saheb-section of old NH-72 NEW NH-07.it is a package-2 of poanta saheb-Mednipur, physical progress is 81.20% and financial progress is 82.75%.The project will serve as a section of Poanta Saheb-section of old NH-72 NEW NH-07.it is a package-2 of poanta saheb-Mednipur, physical progress is 38.90% and financial progress is 36.98%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone