Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : 4L GREENFIELD SPUR FROM DELHI-VADODARA GREENFIELD EXPRESSWAY NEAR BANDIKUI TO JAIPUR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    5

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1636.1501636.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
488.18237.51.16725.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20244/20254/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
187.99344.03

Ministry Review Date

LatestLastPhysical Progress (%)Status
91.22Ongoing

Monthly Status

Background Information

Projects total length is 67Km & physical progress completed till February month is 91.22%.Projects total length is 67Km & physical progress completed till March month is 51.95%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone