Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : SANGARIYA (NEAR CHAUTALA)-RASISAR (NEAR BIKANER) (PHASE-I) (AJ/SR-PACKAGE-2).

Reported Date : 21-AUG-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 8 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
755.160755.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
885.7157.11-187.66755.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20235/20245/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
74.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
95.38Completed

Monthly Status

Background Information

Project total length is 24.30km & cumulative physical progress achieved till March month is 95.25%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone